Energix P2P - UAT Gap Analysis

| 9 min read

Corporate Decisions – Unified (All Territories)

🔴 RED – Go-Live Blocking Corporate Decisions (Frozen)

# Territory Topic Decision Description Go-Live Impact Decision Forum Decision Required By Owner Governance Aspect Decision
C-IL-2 Israel/US Receipt Process not supported by the reality; allow non-receipt for Q1-26 Core process & license cost Steering Committee Go-Live Operations / Finance Inventory & cost governance For Q1-26 the receipt process will be subject to local decision.
C-US-1 Poland/All DocuSign External Signature Contracts sent to suppliers; budget hidden Compliance / exposure CIO Go-Live CIO External compliance The functionality should works for Go-Live
C-US-10 US Agreement vs PR Validation No validation when Agreement < PR while PR is multiple services/suppliers Financial control gap Corporate Finance Go-Live Finance Audit / SOX Decision made - Requisition will be for one service only - Requisition = Agreement
C-US-14 US EPC Services – Retainage Retainage only on PO lines; accounting risk Financial risk Corporate Finance Go-Live Finance Revenue & liability recognition Should be done by Buyer

🟠 AMBER – Corporate Decisions (Tracked, Not Blocking Go-Live)

# Territory Topic Description Impact Solution / Workaround Solution quality Decision Forum Decision Required By Owner Governance Aspect Status
C-PL-1 Poland O&M Budget Management O&M budget visibility & ownership (Tiago) Significant for controlling & reporting by budget manager Working as of today in Q1, Full visibility as budget manager by end of Q1. Poor Corporate Finance Finance Budget governance Pending
C-PL-2 Poland Change Order Training Decision about approval process + Training materials required. Readiness for changes of requesters, allowing buyers to manage the change orders correctly Local decision + training materials Good ERP Go-Live Roey Change management In progress
C-IL-1 Israel Mass POs 2026 Load POs at beginning of 2026 Smoother go-live - The 2026 year's POs will be generated as 2025. Solution for mass load will be supplied by end of Q1 Good Local decision Finance Budget planning Check ongoing
C-IL-3 Israel Non-PO Expenses Rents / taxes / municipal – non-PO policy Requisition is making these POs more difficult to manage - who is the requester for this? Decision needed for allowing part of these expenses to be as invoice without POs Acceptable Steering Committee Finance Policy governance Pending
C-US-8 US Emergency Multi-Supplier No out-of-the-box solution for multi-supplier emergency PR More administration Need to create multiple requisitions for this case. Poor Steering Committee Procurement Process design Example pending
C-US-5 US Emergency PR – Supplier Unknown Supplier required but unknown at PR stage More administration Need to create draft PO for this purpose (as done today) Acceptable Steering Committee Go-Live Procurement Exception governance
C-US-12 US Old POs 2025 → 2026 Handle changes vs close G&A POs; Need assignment of this task for the start of 2026. Sara to manage Acceptable Local Decision Shai Period close control Open
C-US-13 US Goods O&M / EPC Matching Invoice matching: Receipt vs Order for 3-Way More stops for accounting and delays with invoice accounting. Q1 will be time of learning the adapting the solutions. During this period it'll be match to Order. Good Corporate Finance Finance AP & inventory policy Open
C-IL-4 Israel Agreement Header Link Agreement linked to requisition header with line visibility Inability to make requisitions for more than one service/supplier Decision made - Requisition will be for one service only. Poor UX / compliance Steering Committee Amber Contract governance
C-US-6 US Agreement Amount Control Agreement amount should be mandatory / auto-filled from PR No blank is allowed Agreement amount will be required Good Process control Corporate Finance Ambar Contract governance

Local Decisions – US

# Topic Description / Decision Severity (ERP) Go-Live Impact Due Date Status / Notes
L-US-1 Requisition Amount (Materials) Negotiated amount unknown at PR stage Low Usability Go-Live Decision required - When to generate the requisitions - After/Before negotiation
L-US-2 Cross-Company Logistics POs Define requestor (e.g., FedEx) Medium Process clarity -Who will do Go-Live Open
L-US-3 Requestor Definition Legal, Finance, Development requestors High Go-Live risk 14-12-2026 Decision required - Training effectiveness
L-US-4 Receiving Responsibility G&A & O&M receiving ownership Medium Process clarity 21-12-2026 Decision required - Expected shipment role needed for BOL
C-US-11 Multi-Company POs Who should split PR lines across companies: User / Finance / Sara? Medium Process ownership Go-Live Decision required - Sara can be participated in the approval process for correcting documents
C-US-4 Receiving – Shipping & BOL Define what document is required as BOL reference Medium Compliance clarity

Enhancements and Bugs - US

# Topic Description / Decision Severity Workaround Go-Live Impact Decision Forum RAG Status Decision Required By (Go-Live / Date) Owner Management / Governance Aspect Due Date Status / Notes
C-US-3 PR vs Agreement Amount Warning Non-blocking warning if agreement amount > approved PR Medium Red message will be added to the agreement first page. Financial control Corporate Finance Amber Finance control
C-US-5 Delete Lines from PO Bug reported to Oracle Medium Delete only complete PO, solution will be communicated Compliance clarity Steering Committee Amber Logistics policy Decision required

Local Decisions – Poland

# Topic Description / Decision Severity Go-Live Impact Owner Due Date Status / Notes
L-PL-1 Users & Permissions Missing users / employee definitions High Hard prerequisite Before Go-Live List of current users has been sent
L-PL-2 Training Timing Gap between training and operation Medium Adoption risk - Go-live Enhanced support/training will be given to PL
L-PL-3 Multi-Year Contracts Handling of multi-year contracts Medium Process gap Tomasz / Bernadette Q1-2026 Decision pending
L-PL-4 Permissions - Legal department Need purchase agreement access for legal department High prerequisite Jakub Before Go-live List of agreement creators needed

Poland – Bugs

# Bug Description Severity Additional Check / Solution Go‑Live Impact Owner Management Aspect Due Date Notes
B1 Negotiated Flag Flag should appear on user screen Low It seems to be locally for my screen. other users didn't report it. Doesn’t stop go‑live Yaki / Roman UX / usability To be tested
B2 Work Confirmation Duplication Duplicate records in view screen Low But. Will be managed as SR with Oracle. Doesn’t stop go‑live Yaki / Oracle User experience quality Q1-2026
B3 Receipts Visibility Eliza can’t see receipts Medium We've rechecked it and we saw the PO. Please check Doesn’t stop go‑live Yaki / Roman Operational support
B4 Multi‑Company Lines Auto‑reject required High We'll defined auto-reject for Poland, in case of multi-company lines. Required for Go‑Live Yaki Policy enforcement By Go‑Live
B5 PO Workflow Incorrect workflow on PO PLP400111650 Medium Corrected. Please check. Potential control issue Yaki Approval governance To be tested
B6 My Requisition View Eliza & Ewa missing assigning requisitions functionality Low Corrected - Please check Required for Go‑Live Yaki User access Before Go‑Live To be tested
B7 Cancel PO Flow Requisition not appearing after PO cancel Low Oracle bug- managed using SR Doesn’t stop go‑live Yaki / Roman Process consistency By Go‑Live
B8 Requisition Return Notification No notification on return Low Corrected - Please check Doesn’t stop go‑live Yaki Communication To be tested

Poland – Enhancements

# Enhancement Description Severity Go‑Live Impact Owner Management Aspect Due Date Notes
E1 Old Contracts Migration Decide which old contracts to migrate Medium Optional for go‑live Legal Legal governance By Go‑Live Info required
E2 FYI to Procurement Notification to initiate PO Low Improves efficiency Yaki Operational efficiency By Go‑Live
E3 Work Confirmation Access Requester + Buyer only Medium Process clarity Segregation of duties
E4 Subaccount Deductible Subaccounts ending with 11 only Low Configuration Yaki / Roman Finance configuration By Go‑Live Ready for approval
E5 Subaccount by PO Category Limit subaccounts by category Low Configuration Yaki / Bartosz Finance governance Done
E6 LE Default for PMs Default LE based on PM project Low UX improvement Yaki Master data governance By Go‑Live Solution ready for discussing

Corporate Decisions – Unified (All Territories)

🔴 RED – Go-Live Blocking Corporate Decisions (Frozen)

# Territory Topic Decision Description Go-Live Impact Decision Forum Decision Required By Owner Governance Aspect Decision
C-IL-2 Israel/US Receipt Process not supported by the reality; allow non-receipt for Q1-26 Core process & license cost Steering Committee Go-Live Operations / Finance Inventory & cost governance For Q1-26 the receipt process will be subject to local decision.
C-US-1 Poland/All DocuSign External Signature Contracts sent to suppliers; budget hidden Compliance / exposure CIO Go-Live CIO External compliance The functionality should works for Go-Live
C-US-10 US Agreement vs PR Validation No validation when Agreement < PR while PR is multiple services/suppliers Financial control gap Corporate Finance Go-Live Finance Audit / SOX Decision made - Requisition will be for one service only - Requisition = Agreement
C-US-14 US EPC Services – Retainage Retainage only on PO lines; accounting risk Financial risk Corporate Finance Go-Live Finance Revenue & liability recognition Should be done by Buyer

🟠 AMBER – Corporate Decisions (Tracked, Not Blocking Go-Live)

# Territory Topic Description Impact Solution / Workaround Solution quality Decision Forum Decision Required By Owner Governance Aspect Status
C-PL-1 Poland O&M Budget Management O&M budget visibility & ownership (Tiago) Significant for controlling & reporting by budget manager Working as of today in Q1, Full visibility as budget manager by end of Q1. Poor Corporate Finance Finance Budget governance Pending
C-PL-2 Poland Change Order Training Decision about approval process + Training materials required. Readiness for changes of requesters, allowing buyers to manage the change orders correctly Local decision + training materials Good ERP Go-Live Roey Change management In progress
C-IL-1 Israel Mass POs 2026 Load POs at beginning of 2026 Smoother go-live - The 2026 year's POs will be generated as 2025. Solution for mass load will be supplied by end of Q1 Good Local decision Finance Budget planning Check ongoing
C-IL-3 Israel Non-PO Expenses Rents / taxes / municipal – non-PO policy Requisition is making these POs more difficult to manage - who is the requester for this? Decision needed for allowing part of these expenses to be as invoice without POs Acceptable Steering Committee Finance Policy governance Pending
C-US-8 US Emergency Multi-Supplier No out-of-the-box solution for multi-supplier emergency PR More administration Need to create multiple requisitions for this case. Poor Steering Committee Procurement Process design Example pending
C-US-5 US Emergency PR – Supplier Unknown Supplier required but unknown at PR stage More administration Need to create draft PO for this purpose (as done today) Acceptable Steering Committee Go-Live Procurement Exception governance
C-US-12 US Old POs 2025 → 2026 Handle changes vs close G&A POs; Need assignment of this task for the start of 2026. Sara to manage Acceptable Local Decision Shai Period close control Open
C-US-13 US Goods O&M / EPC Matching Invoice matching: Receipt vs Order for 3-Way More stops for accounting and delays with invoice accounting. Q1 will be time of learning the adapting the solutions. During this period it'll be match to Order. Good Corporate Finance Finance AP & inventory policy Open
C-IL-4 Israel Agreement Header Link Agreement linked to requisition header with line visibility Inability to make requisitions for more than one service/supplier Decision made - Requisition will be for one service only. Poor UX / compliance Steering Committee Amber Contract governance
C-US-6 US Agreement Amount Control Agreement amount should be mandatory / auto-filled from PR No blank is allowed Agreement amount will be required Good Process control Corporate Finance Ambar Contract governance

Local Decisions – Israel

# Topic Description / Decision Severity Go-Live Impact Decision Forum Owner Due Date Status / Notes
L-IL-1 Absolute GL Budget Absolute budget should not apply at go-live Critical Blocker if applied Local Mgmt Adi Raanan 21-12-2026 Decision required

Israel – Enhancements

# Enhancement Description Severity Go‑Live Impact Owner Management Aspect Due Date Notes
IL‑E1 Categories List New categories with initials Medium Required for readiness Shiran / Yaki Master data By Go‑Live
IL‑E2 Auto Load Requisitions Automated loading Medium Post go‑live value Yaki Automation 01‑Mar‑2026
IL‑E3 Attachments Category Optional default change Low UX Yaki Configuration By Go‑Live
IL‑E4 DocuSign Logo Energix logo in emails Low Branding Yaki Corporate branding By Go‑Live
IL‑E5 Approval Reminders Reminder after 2 days Medium Cycle time Yaki Workflow governance By Go‑Live
IL‑E6 RNI Report Received not invoiced report Medium Financial control Yaki Finance reporting Done. Please check
IL‑E7 Daniel as Approver Limited to Ops & specific categories Medium Approval governance Daniel Delegation of authority To receive logic and approval from Daniel
IL‑E8 Change Order Flow Requester creates, Buyer submits High Required for Go‑Live SoD / control Done. please check
IL‑E9 IL Construction Org Logic required Medium Data model Org governance Solution ready to present
IL‑E10 Project–LE Mapping Limit LE by PM High Required for Go‑Live FP&A Financial governance Solution ready to present Mapping required

Israel – Bugs

# Bug Description Severity Go‑Live Impact Owner Management Aspect Due Date Notes
IL‑B1 PM Name Change PM to Yaron Low Data correctness Shiran Master data
IL‑B2 Project Split Distribution bug (ILR10010) High Financial accuracy Yaki / Roman Finance integrity Retest required
IL‑B3 Agreement Approval Wrong workflow (850 / ILPA10009) High Control issue Yaki Approval governance Done Please check
IL‑B4 Project Task Mapping Review required Medium Cost allocation Shiran Project governance By Go-Live
IL‑B5 LE in PO Line LE not working properly High Blocker Yaki Legal & financial compliance By Go‑Live
IL‑B6 My Receipt Nir Perez can’t see receipt Medium Ops visibility Roman User access By Go‑Live
IL‑B7 Invoice Workflow Wrong approvers (1234 / ILP180110853) High Financial control Oracle CSS Compliance By Go‑Live
IL‑B8 Negotiated Flag Appears in quick screen Low UX Usability Done Please check

1‑Page Executive Summary (Go‑Live Readiness & Decisions)

🔴 Red – Go‑Live Blockers / Steering Committee Attention

  • Israel – Absolute GL Budget (Local): Hard stop must not apply at go‑live.
  • Israel – Legal Entity in PO Line (Bug): Must be corrected before go‑live.
  • Poland – Users & Permissions: Missing users block operational readiness.
  • Poland – Invoice Approval Not Tested: Testing required before go‑live.

🟠 Amber – Go‑Live Sensitive / Requires Monitoring

  • Mass POs 2026 (Israel, Corporate): Planning decision impacts 2026 execution.
  • Multi‑Year Contracts (Poland): Process clarification required.
  • Project–LE Mapping (Israel): FP&A mapping required.
  • Change Order Process (Israel): Final confirmation before go‑live.
    • Israel – Receipt with BOL (Corporate): Hard stop due to lack of resources; decision required to allow non‑receipt.

🟢 Green – Agreed / Does Not Block Go‑Live

  • Invoice tolerance (5%) aligned with other territories.
  • FYI notifications via DocuSign.
  • Subaccount mappings completed.
  • Branding / UX improvements.

Key Management Forums

  • Steering Committee: Red items, corporate policy exceptions, hard stops.
  • Corporate Finance: Budget controls, non‑PO policy, Mass POs.
  • Local Management: Users, training, local readiness.